Project: |
Dubai Metro Tunnelling Facility |
Location: |
Al Ras, Dubai |
Project Details: |
Design, manufacture, supply, install, test and commission high lift Double Girder gantry cranes handling concrete tunnel segments and skips of excavated material from tunnel boring machines |
Capacity: |
32 tonnes |
Span: |
13 Metres (8m cantilevers each side) |
Height of Lift: |
45 Metres |
Comments: |
Crane installation carried out by Ace Group in only 12 hours (see below pics), Crane also designed to travel on a curved track due to limited space available within the confined area of the site in the commercial centre of Dubai city. |